Larger systems are typically installed at commercial, industrial or rural sites.
Step 1: Read the following
- Distributed generation >10kW information
- Technical requirements for the connection of distributed generation
Step 2: Apply to Wellington Electricity via email and send the initial application fee
Step 3: Wellington Electricity will contact you to acknowledge your application and to discuss any further information or design work that is required
Step 4: Complete the final application form and submit it to us via email
Step 5: Once your final application is approved you will need to send Wellington Electricity your notice to proceed in writing
Step 6: Wellington Electricity will contact you to negotiate a connection agreement to our network. Once the terms and conditions of connection are agreed you will be given approval to proceed with the connection. For reference a copy of this agreement can be found below.
Related Documents
Need help on your distributed generation project?
- If you'd like to talk to one of our project managers about your distributed generation project, please contact us on 0800 248 148 or email We_Projectmanagers@welectricity.co.nz
To help improve our service, what feedback can you give us about this page?